Circuit Breaker

Key Takeaways

  • The US power grid is facing the need for unprecedented levels of investment to accommodate growing demand for electricity and facilitate the transition to other power sources

  • A significant bottleneck to the energy transition is the lengthy and uncertain project permitting process, which can be exacerbated by opposition from existing power generators

  • The modernization of the grid has also been delayed due to shortages of specialized labor, such as lineworkers, and raw materials, like transformers and steel

The upgrade and expansion of the US power grid is the biggest bottleneck and the biggest threat to the energy transition, in our opinion. US electricity demand is expected to grow significantly in the coming years on the back of manufacturing reshoring as well as new data centers, electric vehicles, and building electrification. Grid interconnection, be it transmission or distribution, is aging, requiring upgrades or replacement. Proposed energy projects are mired in lengthy and uncertain permitting processes that are backlogged for years and sometimes ultimately cancelled. Specialized labor, which is currently in short supply, will need to grow by at least 50 percent to meet future grid investment needs.1

Electric Grid Infrastructure

Significantly larger investments will have to be made in the power grid to support the rollout of 3x the amount of renewables needed to replace fossil fuel generation. This could amount to an increase in investment of 5x to 10x historical levels, as not only is there a need for more capacity, but also the majority of the grid is near the end of its useful life.1 Utilities are also shifting existing power lines underground to reduce damage, which would require additional capital expenditures.

US annual transmission and distribution spend is expected to rise 25 percent from $78 billion today to $98 billion by 2050, and of all incremental grid spend through 2050, around 70 percent of that is expected to happen at the distribution level.2

To bring the US to meet the demand and service the electricity supply bottlenecks, the US will need 47,300 GW-miles of new transmission by 2035, a 57 percent increase compared to today’s transmission system, according to the Department of Energy (DoE). “It takes an average of 3 years to construct new facilities. The lead times on major electrical equipment are months long,” said former infrastructure planning executive at PJM Interconnection, part of the Eastern Interconnections.

Transformers are the biggest and most expensive system in the substation. Over 90 percent of the electricity consumed in the US passes through large power transformers, making them the backbone of the nation’s high voltage bulk-power system. There is a multi-decade replacement program underway in the US as installed transformers pass their 35-year life span. Lead times for large transformers have increased to 120 weeks on average this year.3

The bottleneck is due to short supply of grain-oriented electrical steel (GOES), a material critical to the performance of transformers. Commodity prices for GOES have doubled since January 2020, while copper prices have increased approximately 50 percent over the same time frame. Prices have eased but are expected to be volatile going forward due to capacity constraints and growing demand.

Source: GQG Partners. CRS, adapted from U.S.-Canada Power System Outage Task Force.

Permitting

Currently there are an estimated 10,000 renewable energy projects, representing nearly 2.6 Terawatts of power, seeking permission to connect to the grid, twice the number from two years back. It takes five years for the typical power plant to get approval, twice the time it did a decade ago. The surge in new power generation capacity is due to federal tax incentives, including the Inflation Reduction Act (IRA), state clean energy policies, and corporate demand for renewable power sources. In fact, renewables accounted for over 95 percent of all incremental capacity by the end of 2023.4

The Federal Energy Regulatory Commission (FERC) has started to streamline the approval process by ordering grid managers to study projects in bundles and prioritize those that are closest to construction, but an overlooked issue is the opposition by power generation businesses.

“If you look carefully in some of the dockets of various public utility commissions around the country, you will find that sometimes whenever a new utility line is being proposed, generators will often officially become party to the case in order to oppose the transmission line,” said a former chairman of a US public utility commission.

“They’ll come up with some reason like it’s unneeded, it’s a waste of taxpayer money, it’s unreasonable seizure of private land, but the reality is they don’t want more supply to get to the market because they have that part of the market cornered. That’s another conflict that is hiding just beneath the surface.”

To substantially increase renewables, we believe regulations around land access will need to be updated—especially around densely populated areas—to provide the land required for renewables. Yet many of the property owners of those areas do not want high-powered transmission lines, wind turbines, or solar panels in their back yards. Solar requires roughly 10 to 20 times more land than gas, and onshore wind up to 200 times more, to generate the same amount of electricity.5

In addition, a web of factors such as access to electric transmission, conflicts over competing land use, and environmental degradation must be navigated through multiple federal, state, and local regulatory permitting processes.

Labor Shortages

There are currently 120,000 linemen working in the US grid. However, to modernize and expand the grid, it is estimated that the industry will need at least 178,000 linemen by 2035, or a 50 percent increase. Sourcing this labor is challenging because they are skilled craftsmen with at least five years of training and experience needed.6

It is estimated there are more than 21,000 lineman job openings this year and demand is expected to climb by 8.5 percent by 2026. The high demand in this specialized craft is due to a) decline in enrollment due to lack of interest by the new generation; b) retirement of experienced linemen and age out of the workforce; c) the rapid rise in transmission and distribution projects needed to strengthen the grid.7

“This labor challenge is common throughout the utility industry. As lots of folks are retiring, the current challenge is to hire and retain people. There’s a significant amount of training that goes into getting folks performing work safely, especially the field-based positions. A lot of the younger workforce want gigs. They want jobs that they can pop in and pop out of with little commitment to a longer-term employer. This is going to continue to be a challenge,” said a former tenured employee at a US utility.

Swift Action Needed

We believe US regulators are moving in the right direction by recently approving sweeping changes to upgrade and expand the country’s decrepit infrastructure. But addressing the logistical and political challenges of constructing new power lines across states is yet to be seen. Supply chain disruptions, including shortages of raw materials for critical equipment, as well as a deficit in specialized labor, are expected to intensify the electricity supply/demand imbalance in the coming years.

Read more about US energy supply and explore what is driving the surge in demand

PJM is a regional transmission organization that coordinates the movement of wholesale electricity in all or parts of the North Eastern interconnection grid operating in 13 states and the District of Columbia.

1Dillard, Chad et al. “The Electric Butterfly Effect: Rising electricity demand, the role of the grid and the critical bottlenecks.” Bernstein Research. March 27, 2024.

2“Americans for a Clean Energy Grid and Grid Strategies Release New Report on Declining Large-Scale Transmission Construction in the U.S.”, Americans for a Clean Energy Grid, July 30, 2024.

3The National Infrastructure Advisory Council. “Addressing the Critical Shortage of Power Transformers to Ensure Reliability of the U.S. Grid “, CISA.gov, June 2024.

4Plumer, Brad. “A Bottleneck on the Grid Threatens Clean Energy. New Rules Aim to Help.” New York Times, July 27, 2023.

5Jamie Brick, Jamie, Dediu, Dumitru and Noffsinger, Jesse. The role of natural gas in the move to cleaner, more reliable power”, McKinsey & Company, September 1, 2023.

6”Lineman Central Verified Data Report: Lineman and Powerline Statistics”, Lineman Central.

7Kortnoy, Billy. “2024 Lineman Jobs are in High Demand”, Lineman Central, December 21, 2023.

“Grid connection backlog grows by 30% in 2023, dominated by requests for solar, wind, and energy storage”, Energy Markets & Policy, Berkeley Lab, April 20, 2024.

IMPORTANT INFORMATION

This information may be distributed by GQG Partners LLC and its affiliates (collectively “GQG”).

This information reflects the views of GQG as at a particular time. GQG’s views may change without notice. Any forward-looking statements or forecasts are based on assumptions and actual results may vary.

GQG provides this information for informational purposes only. GQG has gathered the information in good faith from sources it believes to be reliable, including its own resources and third parties. However, GQG does not represent or warrant that any information, including, without limitation, any past performance results and any third-party information provided, is accurate, reliable, or complete, and it should not be relied upon as such. GQG has not independently verified any information used or presented that is derived from third parties, which is subject to change. Information on holdings, allocations, and other characteristics is for illustrative purposes only and may not be representative of current or future investments or allocations.

NOTICE TO RECIPIENTS IN AUSTRALIA & NEW ZEALAND

The information in this document is issued and approved by GQG Partners LLC (“GQG”), a limited liability company and authorised representative of GQG Partners (Australia) Pty Ltd, ACN 626 132 572, AFSL number 515673. This information and our services may be provided to wholesale and retail clients (as defined in section 761G of the Corporations Act 2001 (Cth)) domiciled in Australia. This document contains general information only, does not contain any personal advice and does not take into account any prospective investor’s objectives, financial situation or needs. In New Zealand, any offer of a Fund is limited to ‘wholesale investors’ within the meaning of clause 3(2) of Schedule 1 of the Financial Markets Conduct Act 2013. This information is not intended to be distributed or passed on, directly or indirectly, to any other person.

NOTICE TO RECIPIENTS IN CANADA (Alberta, British Columbia, Manitoba, New Brunswick, Nova Scotia, Ontario, Québec, Saskatchewan (the “Canadian Jurisdictions”))

GQG Partners LLC relies on the (i) international adviser exemption pursuant to section 8.26 of NI 31-103 in each of the Canadian Jurisdictions, and (ii) non-resident investment fund manager exemption pursuant to section 4 of MI 32-102 in Ontario and Québec and is not registered as an adviser or investment fund manager in the Canadian Jurisdictions.

This document has been prepared solely for information purposes and is not an offering memorandum or any other kind of an offer to buy or sell or a solicitation of an offer to buy or sell any security, instrument or investment product or to participate in any particular trading strategy. It is not intended and should not be taken as any form of advertising, recommendation, investment advice or invitation to trade. This information is confidential and for the use of the intended recipient only. The distribution of this document in Canada is restricted to recipients who are qualified “permitted clients” for purposes of National Instrument 31-103 Registration Requirements, Exemptions and Ongoing Registrant Obligations. This document may not be reproduced, redistributed or copied in whole or in part for any purpose without the prior written consent of GQG. Upon receipt of this document, each Canadian recipient hereby confirms having expressly requested that all documents evidencing or relating in any way to the information described herein be drawn up in the English language only. Par la réception de ce document, le détenteur au Canada de celui-ci confirme par les présentes avoir expressément exigé que tous les documents faisant foi ou se rapportant de quelque manière que ce soit aux informations présentées dans ce document soient rédigés en anglais seulement.

NOTICE TO RECIPIENTS IN SOUTH AFRICA

GQG PARTNERS LLC is an authorised financial services provider in the Republic of South Africa and regulated by the Financial Sector Conduct Authority (FSCA) with FSP number: 48881. Investors should take cognisance of the fact that there are always risks involved when buying or selling any financial product. Past performance of a financial product is not necessarily indicative of future performance. The value of financial products can increase as well as decrease over time, depending on the value of the underlying securities and prevailing market conditions. The investment value of a financial product is not guaranteed, and any illustrations, forecasts or hypothetical data are provided for illustrative purposes only. This document does not constitute financial advice, a solicitation, invitation or investment recommendation. Prior to selecting a financial product or investment, it is recommended that South African based investors seek and obtain specialised financial, legal and tax advice.

NOTICE TO RECIPENTS IN THE UNITED KINGDOM

GQG Partners LLC is not an authorised person for the purposes of the Financial Services and Markets Act 2000 of the United Kingdom (“FSMA”) and the distribution of this document in the United Kingdom is restricted by law. Accordingly, this document is provided only for and is directed only at persons in the United Kingdom reasonably believed to be of a kind to whom such promotions may be communicated by a person who is not an authorised person under FSMA pursuant to the FSMA (Financial Promotion) Order 2005 (the “FPO”). Such persons include: (a) persons having professional experience in matters relating to investments; and (b) high net worth bodies corporate, partnerships, unincorporated associations, trusts, etc. falling within Article 49 of the FPO. The services provided by GQG Partners LLC and the investment opportunities described in this document are available only to such persons, and persons of any other description may not rely on the information in it. All, or most, of the rules made under the FSMA for the protection of retail clients will not apply, and compensation under the United Kingdom Financial Services Compensation Scheme will not be available.

GQG Partners (UK) Ltd. is a company registered in England and Wales, registered number 1175684. GQG Partners (UK) Ltd. is an appointed representative of Sapia Partners LLP, which is authorised and regulated by the Financial Conduct Authority (“FCA”) (550103).

NOTICE TO RECIPIENTS IN ADGM

GQG Partners Ltd, a company limited by shares, registered in Abu Dhabi Global Markets (“ADGM”), having its address at Unit 12, 7th Floor, Al Khatem Tower, Al Maryah Island, Abu Dhabi, United Arab Emirates. GQG Partners Ltd is licensed by the ADGM’s Financial Services Regulatory Authority (FSRA) (license number 240015). GQG Partners Limited is licensed by the ADGM’s Financial Services Regulatory Authority (FSRA) to conduct the regulated activities of Managing a Collective Investment Fund, Advising on Investments or Credit, Arranging Deals in Investments, Managing Assets, Shari’a-compliant Regulated Activities. This document is intended for distribution only to persons of a type specified in the FSRA’s Rules (i.e., “Professional Clients”) and must not be delivered to or relied on by any other type of person. It is for the exclusive use of the persons to whom it is addressed and in connection with the subject matter contained therein. The FSRA, or any other regulatory authority, has no responsibility for reviewing or verifying this document or any other document in connection with it. Accordingly, the FSRA, or any other regulatory authority, neither approved this document or any other associated documents nor taken any steps to verify the information set out in this document and has no responsibility for it.

 © 2024 GQG Partners LLC. All rights reserved. This document reflects the views of GQG as of September 2024.

TL PWRIMBL-3 0724